The pump set built in this article: two horizontal split-case pumps, a suction header, a discharge header and the riser Photo: Revit 2027 screenshot, Institute sample file linked to Autodesk's Snowdon Towers architectural model

A pump room is the tightest, most crowded space in a fire protection system. On a CAD drawing the pump set is a few rectangles and a thicket of lines; to find out whether a pipe runs into a plinth you have to draw another section, line by line.

Building a fire pump room in revit gives you something else: the pump is equipment with connectors, pipe snaps straight onto those connectors, valve sets cut into the pipe, and the whole assembly can be grouped for the next project. Fourteen steps on Revit 2027, each saying what to click and what appears. For the wider subject, see the Institute's Revit MEP course.

What a pump room is made of in Revit

Before drawing, know which kind of object each item is. Put something in the wrong category and it will neither schedule nor connect.

Item in the pump roomCategory in RevitCommand
Fire pump, jockey pumpMechanical EquipmentSystems › Mechanical › Mechanical Equipment (ME)
Pressure vessel, air receiverMechanical Equipmentas above
Suction header, discharge header, riserPipesSystems › Plumbing & Piping › Pipe (PI)
Gate and check valves, foot valve, Y-strainerPipe AccessoriesSystems › Plumbing & Piping › Pipe Accessory (PA)
Hose cabinet, landing valve on the riserPipe Accessories or Mechanical Equipment, depending on the familyType Selector of that command
Elbows, tees and couplings between pipesPipe Fittings, generated by Revitnot placed by hand

The fire pump room in revit shown here is built in an empty bay of the basement to keep the focus on the commands. Room size, number of pumps, header sizes and the valve arrangement come from the approved design, under the codes in force.

The file to follow along with

This article uses the exercise file described in Revit MEP sample files: a copy of the Institute's fire protection template linked to the Snowdon Towers model shipped in the Samples folder of Revit 2027. The basement is Floor Plans › Parking.

The template carries a pump room kit: the horizontal split-case pump Pump-Horizontal_Multi_Stage-Split_Case_Fire-Aurora_Pump-481, a jockey pump, the pressure vessel Grundfos_Pressure_Vessel, the butterfly valve FP-Accessory-ButterflyValve in four sizes, check and foot valves (Check_Valve-Metraflex-Foot_Valve), a Y-strainer, the hose cabinet FF-Equipment-FireBox and the landing valve FF-Equipment-HoseValve. With another template, swap in your own equivalents.

Placing a fire pump revit family and reading its connectors

Step 1. Open Floor Plans › Parking and zoom to the bay that will hold the pump room.

Step 2. Click Systems › Mechanical › Mechanical Equipment, shortcut ME.

Step 3. Open the Type Selector and type Pump into the search box. The list narrows to the pump families in the file. Pick the fire pump type and click where it goes.

1 the Type Selector search box, 2 the fire pump type carried by the template, 3 the pump placed on the basement plan Photo: Revit 2027 screenshot, Institute sample file linked to Autodesk's Snowdon Towers architectural model

Step 4. Place the second pump beside the first. Repeat step 3 for the jockey pump and the pressure vessel if the design has them.

Step 5. Select a pump. The 2027 release draws each connector's label in the view: size, flow direction and type. This pump has two 125 mm pipe connectors — one Out, the discharge, one In, the suction — plus an electrical connector.

1 the discharge connector, flow direction Out, 2 the suction connector, direction In, 3 the Select Connector dialog listing those same two connectors when you connect a pipe Photo: Revit 2027 screenshot, Institute of Information Technology in Civil Engineering

Suction header, discharge header and connecting the pumps

Step 6. Start the Pipe command (PI). In Properties choose the pipe type, then type a Diameter for the header and a Middle Elevation — the centreline height above the level. Check that Reference Level reads the basement.

Step 7. Draw the discharge header in front of the row of pumps: click the start point, click the end point, press Esc twice.

Step 8. Draw the suction header behind the row the same way.

1 centreline elevation, 2 header diameter, 3 the discharge header in front of the pumps, 4 the suction header behind them Photo: Revit 2027 screenshot, Institute sample file linked to Autodesk's Snowdon Towers architectural model

Step 9. Connect the discharge: select the pump and click Modify | Mechanical Equipment › Layout › Connect Into. The Select Connector dialog lists the pump's connectors; pick the line that reads Discharge Outlet Connection and click OK. The cursor gains a plus sign; click the discharge header. Revit builds the connection and inserts a tee.

Step 10. Connect the suction: repeat step 9 and pick Suction Inlet Connection, or start the Pipe command on the suction connector itself and click the suction header as the second point.

1 the Connect Into button in the Layout panel, 2 the discharge connection Revit builds, 3 the suction branch down to the header Photo: Revit 2027 screenshot, Institute sample file linked to Autodesk's Snowdon Towers architectural model

With the pipework connected, open the System Browser with F9: each run into a pump becomes a named system, and nothing from the pump room is left under Unassigned. Systems and their hierarchy are covered in systems in Revit MEP.

The valve set and the riser

Step 11. Place a valve: click Pipe Accessory (PA), type the family name in the Type Selector search box, pick the size that matches the pipe and click the pipe. The valve breaks the pipe and joins both ends. A valve set on each pump usually means isolating valves either side and a check valve on the discharge; place them one at a time from the schematic.

1 the search box and the sizes of the butterfly valve family in the template, 2 the valve on the first pump branch, 3 the valve on the second Photo: Revit 2027 screenshot, Institute of Information Technology in Civil Engineering

Step 12. The riser: start the Pipe command, click a point at the end of the discharge header, change Middle Elevation to the level above and click Create Riser in the Placement Tools panel. Revit builds the vertical run between the two elevations. That button is new in the 2027 release.

1 the Create Riser button, 2 the new value typed into Middle Elevation, 3 the vertical pipe seen in a 3D view Photo: Revit 2027 screenshot, Institute of Information Technology in Civil Engineering

The riser then feeds hose cabinets or landing valves floor by floor. Heads and branch pipework on a typical floor are covered in modelling sprinklers in Revit.

Grouping the pump set for reuse

Step 13. Select the whole assembly, then click Modify | Multi-Select › Create › Create Group, shortcut GP. In the Create Group dialog type a name, leave Group Type on Model and click OK.

1 the Name box of the Create Group dialog, 2 the pump set on the plan once it is a group Photo: Revit 2027 screenshot, Institute sample file linked to Autodesk's Snowdon Towers architectural model

To edit it, double-click the group: an Edit Group bar appears with Add, Remove, Attach, Finish and Cancel. You must click Finish, otherwise the whole project stays in group-edit mode.

To carry the set into another project, Autodesk gives the route on the Save Groups page: File › Save As › Library › Group, pick the group and save; the next project loads it with Insert › Load as Group.

Scheduling the equipment

Step 14. Go to View › Create › Schedules › Schedule/Quantities. Type Mechanical Equipment into Category name search, pick the category and click OK. On the Fields tab add Family and Type and Count; on Sorting/Grouping clear Itemize every instance, tick Grand totals and click OK.

1 the two fields moved into Scheduled fields, 2 the result: one row per type with its count and a grand total Photo: Revit 2027 screenshot, Institute of Information Technology in Civil Engineering

A valve schedule works the same way with the Pipe Accessories category, plus the Size field to separate the sizes. Exporting to Excel is covered in schedules in Revit.

From fire pump cad blocks to Revit families

People coming from CAD look for fire pump cad blocks or a set of pump and valve symbols to drop into the drawing. In Revit each of those symbols is a family carrying data, and that data is what produces the quantities.

On the CAD drawingIn Revit 2027
Plan and elevation blocks of a pumpOne Mechanical Equipment family with 3D geometry and suction and discharge connectors
A valve blockA Pipe Accessory that breaks the pipe and joins both ends
Pipe drawn by hand to scalePipe with a size, an elevation and a system
A pump room section redrawn from scratchA section cut from the model that updates when the model changes
A parts list typed by handA schedule that recounts whenever the model changes

The old drawing still helps: Insert › Link CAD brings the schematic or the old plan in as an underlay to place equipment over.

When it does not behave

What you seeWhyWhat to do
A window selection grabs the whole architectural model, and dragging moves itThe linked model sits under everything, so it is easy to hitTurn Select Links off at the right end of the status bar while selecting, then back on
Revit warns "The family is connected in a network and can no longer keep the connectivity"You have just dragged the link that hosts equipmentClick Cancel to abandon the move
Connect Into gives no Select Connector dialogThe pump has only one free connector left, so Revit skips the questionClick the pipe straight away
The connection runs at an angle instead of squareThe pump connector is not in line with the headerDraw it by hand: straight out of the connector, then square into the header
A valve refuses to go in, or reducers appear around itThe valve size differs from the pipe sizePick the valve size that matches, or resize that run first
Every view stays washed out after editing a groupYou are still in group-edit modeClick Finish on the Edit Group bar
1 the Select Links toggle at the right end of the status bar: switch it off and a window selection ignores the linked model Photo: Revit 2027 screenshot, Institute of Information Technology in Civil Engineering

Frequently asked questions

Which category does a fire pump belong to?

Mechanical Equipment, from Systems › Mechanical › Mechanical Equipment, shortcut ME. The family needs pipe connectors before pipe will snap to it.

Where do pump families come from?

From the Institute template, from a manufacturer's .rfa loaded with Insert › Load Family, or built yourself as in creating families in Revit.

Why group the pump set?

Because pump rooms repeat between projects. A group keeps the connections intact, saves out through File › Save As › Library › Group and comes back with Insert › Load as Group.

Does Revit calculate head and flow for the pump set?

Not for fire protection. Flow, head and the number of pumps come from a separate calculation, under the codes in force and the approved submission.

How do I get a section through the pump room?

Cut one with View › Section. The section comes from the model, so editing the pipework updates the drawing instead of forcing a redraw.